Basel

The installation of the new operations center in the inner courtyard with the necessary demolition of the existing AEH and the seismic upgrades must be carried out while ensuring 24-hour operation of the existing operations center. It may only be shut down when the new operations center is ready for operation. Subsequently, seismic retrofitting measures in the old building and the renewal of the building services will be carried out during ongoing operations. The tight conditions due to the inner-city location with pedestrian, car and streetcar traffic represent a further challenge that should not be underestimated, taking into account the preservation of historical monuments.

Owner
Building and Transport Department Canton Basel-Stadt

Project parties
Architecture: TrinklerStulaAchille Architekten AG, Basel

Project details
Project type: recinstruction
Use: office & administration
Project start: 2013
Completion: 2025
Concstruction costs: approx. CHF 48.5 million
Volume according to SIA 416: 9’282 m3
Floor area according to SIA BGF: 12’306 m2

Caretta Weidmann
Services: general planning, overall management, construction management, construction economics/cost planning